Share

Cost Items

Cost items are individual items in a change order that are linked to associated budgets and contracts. They can be viewed, dynamically grouped, and filtered in multiple ways in the Cost Item tab.

Note: The data contained in a cost item is the same information entered for a PCO (Potential Change Order). At least one cost item must be added to a PCO to generate change orders.

Cost items include five values:

  • Estimated: For one PCO, a general contractor (GC) estimates the value.
  • Proposed: The GC asks the supplier to provide the estimation of the cost item of an RFQ (Request For Quotation) and records the estimation into the Proposed value.
  • Submitted: The cost item value appears in the Submitted column when a GC submits the COR (Change Order Request) for an owner's review.
  • Approved: After an owner's initial review, a GC combines multiple CORs into one OCO (Owner Change Order) and signs the legal change order document with the owner. The OCO value is recorded as Approved.
  • Committed: After the OCO or COR is approved, a GC signs an SCO (Subcontractor Change Order) with the supplier. The value is recorded as Committed.

Cost item's values populate in the Change Order tool's tables:

Cost items values table

Note: The data contained in a cost item is the same information entered for a PCO (Potential Change Order). At least one cost item must be added to a PCO to generate change orders.

Learn more about Cost item statuses.

In this article:

Add a Cost Item

Cost items can be added in the Cost Item tab:

  1. Click the Change Order tool from the left navigation.
  2. Switch to the Cost Item tab.
  3. Click Add.
  4. Enter a name for the cost item.
  5. Select a Budget Code from the drop-down list.
  6. Enter an estimated price.
  7. Select a Location for the cost item from the location breakdown structure.
  8. Select the checkbox next to the cost item.
  9. Click Assign.
  10. Select a PCO from the PCO drop-down list.
Tip: After cost items are added, you can edit the items by clicking the budget item and using the panel on the right. You can make these edits from both the Cost Item tab and the PCO tab.

Edit cost item panel

Copy a Location of a Cost Item

If a location for one cost item applies to other cost items within the same PCO, you can copy the location. To do so:

  1. From the PCO tab, hover your cursor over the Location field of the cost item assigned to a PCO.

  2. Click Copy location icon to copy the location to the other cost items in the PCO.

    Copy cost item location

Copy a Cost Item's Amount

You can copy all cost items' amounts of the same change order to the current column:

  1. Click Copy location icon next to the cost item in the Estimated, Proposed, Submitted, Approved, or Committed column.
  2. Choose one of the available values to copy from.

Copy cost item amount

Tip: You can copy values in the Change Order table, the Cost Item table, and when generating a change order or contract.

Add a Cost Subitem

Within individual cost items, you can:

  • Add subitems that roll up into the parent cost item.
  • Define a cost item hierarchy for each of the Estimated, Proposed, Submitted, Approved, and Committed tabs.
  • Determine a subitem hierarchy for each tab or inherit a subitem hierarchy from another tab.
  • Use a hierarchy from a contract schedule of values (SOV).
  • Import subitems from an Excel spreadsheet.

To add a cost subitem:

  1. Click a cost item name to open the details panel.

  2. Select a tab in the Cost Summary section.

    Note: The tab you select determines which column in a table a subitem total appears in.
  3. Click the Define Hierarchy menu.

  4. Choose between:

    • Start a New Hierarchy: Enter the Code, Name, Quantity, Unit, and Unit Cost for a subitem.
    • Use Hierarchy from Budget: This option is available when the cost item is linked to a budget. Select the checkbox for SOV to use and then click Save.
    • Use Hierarchy from Contract SOV: Select the checkbox for SOV to use and then click Save.

    Define subitem hierarchy

    Note: When an Estimated, Proposed, Submitted, Approved, or Committed value is already provided, you can use its hierarchy by selecting Use hierarchy from ..., for example, Use hierarchy from Proposed.

    Subitem hierarchy options

To add more subitems:

  1. Hover your cursor over the parent or subitem.
  2. Click the More menu Vertical more menu icon.
  3. Click Add Subitem.
  4. Enter the data for the new subitem.
  5. As required, switch between the remaining tabs, click the Define Hierarchy menu, and select one of the available options.

To import subitems from an Excel spreadsheet:

  1. Click the Define Hierarchy menu.
  2. Select Import subitems and Import Excel file.
  3. Choose the file you want to upload, then click Import.

Assign Cost Items to a Potential Change Order

Existing or new cost items created directly in the Cost Item tab can be assigned to a Potential Change Order (PCO). To do so:

  1. Select the checkbox next to the cost item in the Cost Item tab.
  2. Click Assign. You'll see the pop-up window.
  3. Select the PCO to add the cost item. You can type in search criteria to filter the list.
Note: If you need to move budgets between items without changing the total budget, consider using change order transfers. See the Create Change Order Transfers section for more information.

Generate a Change Order

You can generate an RFQ and SCO from a cost item. To do so, click the More menu Vertical more menu icon next to the cost item, and then choose Generate RFQ or Generate SCO from the Generate category.

Generate a Contract from a Cost Item

You can generate a contract from a cost item when the cost item meets the following conditions:

  • The PCO status is one of the following: Open, Pricing, Proposed, Accepted, Revise and Resubmit.

  • The cost item is:

    • Not associated with an existing contract.
    • Not associated with an existing SCO.
    • In the same main contract.
  • The budget of the cost item isn't already allocated to a contract.

To generate a contract from a cost item:

  1. Click the Change Order tool from the left navigation.

  2. Switch to the PCO tab.

  3. Click the checkbox to the left of a cost item within a PCO.

  4. Click Generate, and then Contract.

    Generate contract button

    Tip: You can also click the More menu Vertical more menu icon to the right of a cost item. Choose Generate, and then Contract.

    Generate contract from more menu

  5. Enter a Contract code and a Contract name. If the foreign currency setting is enabled in your project, you'll see the Currency and Exchange Rate fields as well.

    • Choose the currency for your new contract.
    • Edit the exchange rate if needed. The default exchange rate is fetched from the settings.
  6. Enter the committed value or copy it from the cost item. If the foreign currency setting is on, the Converted value icon icon shows the converted value.

  7. Click Generate.

Was this information helpful?