Explore the Resources of the Schedule

The Resources tab displays how resources are employed over the time of your project. Often times, resources are the different departments working on your project, but it doesn't have to.

The Resources tab offers you insights into the evolution resources use over the course of your project, when the Schedule tab and its Gantt chart show the relationships between tasks.

Open the Resources tab to understand how your project's resources usage evolves over time. You can also use the Resources tab to shape how the resources are used over time using Resource Shaping.

resources overview.png

1. Resources overview 2. Zoom controls 3. Activity key 4. Resources details

Resources overview

The Resources overview shows how the different resources classes are used over the course of the schedule. Clicking a resource class in the overview or the Activity key opens it in the Resources details panel.

View the tasks for a resource

You can view all the tasks that make use of a resource class on a specific day.

To view the tasks that require the selected resource class:

  1. Select a resource class.

    You can select it in the Resources overview, the Activity Key panel, or the All Resources table.

  2. In the Resources Details timeline, select a date.

  3. Click Task list in the information panel.

    The Task list display all the tasks that require this resource class, including the number of units of this resource that are required to complete that task.

Zoom in and out of the Resources graphs

Easily zoom in and out of the Resources graphs with the zoom tools:

  • Zoom in and out of the chart with zoom in out. You can also use Ctrl+Scroll wheel while hovering over the chart to zoom.

  • Zoom to a specific date range by entering dates in zoom calendars.

  • Quickly zoom in a range with draw zoom.

    draw zoom animation