Show more detail about the assembly of a component with lists of sub-components or materials . Video: Create a Material Takeoff Schedule Material takeoff schedules list the sub-components or materials of any Revit family.
-
To create a material takeoff schedule Click View tabCreate panelSchedules drop-down Material Takeoff .
-
This video demonstrates the following: Decide the information type to be reported in the material takeoff schedule. Create a material takeoff for concrete in a model.
-
This video demonstrates the following: Decide the information type to be reported in the material takeoff schedule. Create a material takeoff for concrete in a model.
-
This example demonstrates how to create a wall material takeoff schedule with images, but you can use the same procedure to create a material takeoff for other element types.
-
Create schedules, quantities, and material takeoffs to quantify and analyze the components and materials used in a project.
-
Filter by Family and Type parameters in schedule and material takeoff views. This improves family filtering in single-category or multi-category schedules.
-
You can now use system categories and subcategories that were previously not available in multi-category schedules and material takeoffs . This feature enhancement improves Revit scheduling by including additional system categories in multi-category schedules for Schedule/Quantities and Material Takeoffs .
-
The materials in a compound element can be tagged, scheduled, and included in material takeoffs .
-
The creation of Material IDs is required only, if: the Buildingbook data is to be exported into a Schedule, or for exporting to DWF/DWFx for Autodesk Quantity Takeoff .
-
Finish IDs are identifiers for each calculated material per element and are only created if explicitly specified.
-
You can exclude parts from the project so that they will not be included in material takeoffs , schedules, and other lists or calculations.
-
Construction professionals need all of these drawings, as well as schedules and material takeoffs , to build the design.
-
The Filter list displays on the following dialogs: Visibility/Graphics dialog Object Styles dialog View Filters dialog New Schedule dialog New Material Takeoff dialog Schedule Properties dialog, Embedded Schedule tab Project Parameters dialog Loaded Tags dialog
-
Openings in walls, floors and ceilings are detected to adjust the calculated surfaces and the material requirement. All materials of the surfaces are listed.