Change the sequence of results in the report generated in the previous task.
- Click to open the Reports tab.
- Click .
- If there is more than one report in this project, the Select A Project Item dialog appears. Select the tutorial report you want to work with and click OK.
The Report Generation Wizard dialog is opened.
- Click Next until the Report Layout page appears.
- Select cellphone_study:Pressure at end of fill from the Report Items text box. The Item details options are activated.
- Click Move Up to move the Pressure at end of fill result to the top of the list.
- Click Generate. The report has been regenerated, promoting the Pressure at end of fill result and its associated plot notes to the top of the report.