To Create a Drawing List Report

  1. Click Project tabProject Tools panelManager. Find
  2. (Optional) Select drawings or folders in Project Manager.
  3. In the Project Manager, right-click the project name, and select Drawing List Report.
  4. (Optional) In the Drawing List Report dialog box, click Format and browse to a report format file.
  5. Click New Report.
  6. Select the drawings to process.
    Note: Drawings or folders selected in Project Manager are preselected in the Select Drawings to Process dialog box.
  7. Click OK.

    The data is displayed in the Report Generator dialog box so you can change the report format, save to a file, and place the report as a table.