Create a Change Order Numbering Scheme (Vault 2015 Only)

You can use numbering schemes to help organize your change orders.

Note: This topic applies only to Vault 2015. See Numbering Schemes for information about Change Order Numbering Schemes in Vault 2015 R2.

Create a Numbering Scheme

  1. In the Vault Client, Tools > Administration > Vault Settings.
  2. In the Vault Settings dialog box, click the Change Orders tab.
  3. In the Change Order Numbering section, Click Define.

    The Change Order Numbering dialog opens.

  4. In the Change Order Numbering dialog box, click New.
  5. In the Edit/Create Change Order Numbering Scheme dialog box, specify a name for the numbering scheme in the Code field.
  6. In the description field, optionally enter a description of the scheme.
  7. Specify the starting number for the new scheme.
  8. The change order numbering scheme can range from 3 to 6 digits. Select the number of digits to use for the scheme.
  9. Click OK.