Copy Elements to Additional Stories
Learn how to use the Object Inspector to copy the content of a story to other stories.
Please enable Javascript to watch this video.
Go to the
View
tab. All of the elements that you have created can be copied to the other stories.
In the Object Inspector, right-click on Story 1 and select
Stories
>
Copy contents of the story…
as shown below.
Note:
If you did not have additional Stories in the project, you could use
Copy story…
and have the software create the story and copy the contents.
In the Copy contents of a story dialog box, set the
Geometry
to
Above
and the
No. of repetitions
to
4
as shown below.
Click
OK
.
The contents of Story 1 are copied to the other stories as shown below.
Save the project.