To create an overhead transmission network
For more information, see Managing Electric Circuits.
For transmission networks, the breaker must be assigned to a structure, for example a substation.
For more information on pole and tower cross sections, see Defining a Node Cross Section Template in Electric.
When you digitize a conductor that runs across several towers, segments are created automatically between the towers, if not yet existing. For example, you digitize a conductor that runs from a breaker across several towers to the final breaker. Then, when you digitize a second conductor that runs across the same towers, the system will propose snap points that follow the previously created conductor. You do not have to click all the snap points again. Instead, click the final breaker to accept the proposed snap points.