To Generate Rehab Corridor Reports

Generate and export a crossfall adjustment and milling and levelling rehab report for a rehab corridor region.

  1. Click Home tab ModifyCorridorEdit Rehab Corridor .
    Existing rehab corridor regions will be highlighted blue.
    Note: Only corridor regions with rehab subassemblies are available for selection. See Rehab and Crossfall Optimisation Subassemblies to review rehab subassemblies.
  2. Select a rehab region from the corridor.

    The Rehab Corridor Editor ribbon tab for your selected rehab corridor region is displayed and the Rehab Parameters palette will auto-dock to the right side of the application window.

    Note: Three custom viewports will be displayed: the cross section view, profile view and the plan view. See About Rehab Corridor Sections for more information.
  3. Optionally, edit the rehab corridor. When finished with your modifications, click Apply to update the selected rehab corridor region.
  4. Click Rehab Manager in the Rehab Corridor Editor ribbon tab.

    By default, the Crossfall Correction Report tab is selected in the Rehab Manager. You can also select the Milling and Levelling Report tab.

    Note: All chainages in the currently selected rehab corridor region are displayed in the Rehab Manager. Use the chainage selection drop-down menus in the Rehab Manager to restrict reports to a specific chainage range. You can also select a different rehab corridor region with the region drop-down menu or arrows.
  5. Use the Chainage Selection panel in the Rehab Corridor Editor ribbon tab to navigate between chainages in the rehab corridor region. The row will be selected in the Crossfall Correction Report and Milling and Levelling Report tables.

    You can also select a row in the Cross Section Correction Report tab or the Milling and Levelling Report tab to update the cross section view, plan view and profile view for different chainages.

  6. Click within the reports in the Rehab Manager to make any modifications. Your modifications will automatically be applied to the selected rehab corridor region.
    • For Crossfall Correction Report, the Accepted Slope can be modified in the Rehab Manager.
    • For Milling and Levelling Report, there are no fields that can be modified in the Rehab Manager.
  7. Optionally, click Export Report to export the report for the selected chainage range in XML format.
    Note: You can select a different stylesheet to use for the report by modifying the report settings. Click to open the Rehab Report Settings dialog box and specify the Report Style Sheet File options.
  8. Click Close in the Rehab Corridor Editor ribbon tab when done.