Part Use Priority Dialog Box

Sets the order that parts are used based on part size.

List of Options

Part Group

Displays the part group selected in the spec sheet.

Assign Part Use Priority

Size Conflicts

Specifies part sizes. You specify a part size before you can set Priority or Mark as Resolved. You can select more than one size conflict to mark as resolved.

Spec Part Use Priority

Specifies the spec part to modify.

Priority Arrows

Modifies part use priority. You must have a spec part specified to change priority.

Mark as Resolved

Marks the size conflict as resolved. When all sizes are marked resolved, the spec sheet displays a green circle in the spec sheet.