Edit a Workset

When you want to add or edit elements in a workshared project, you must first select the workset to work in.

  1. Select an active workset, using one of the following methods:
    • On the status bar, select the workset from the Active Workset drop-down.
    • Select the workset from the Active Workset drop-down on the Collaborate tabManage Collaboration panel.
  2. If you want all elements that are not in the active workset to be gray, click Collaborate tabManage Collaboration panel (Gray Inactive Worksets).
  3. Edit or add elements in the workset, as necessary.
    Note: If you add view-specific elements, such as detail lines or dimensions, they are added to the workset of the active project view.