PLANTORTHOVALIDATEVIEW

Checks the model to see if changes have been made since the drawing was last updated.

Access Methods

 Shortcut menu:  Project Manager Orthographic DWG tabright-click ortho drawing or view Validate View
 Command entry:  plantorthovalidateview

Summary

After you have created an ortho view, you can validate the view against the 3D model to see if a change has been made. If so, the red highlight on the icon indicates that the view needs updating. Updating an entire drawing with many views can take several minutes, depending on the complexity of the model.