Map Phases Between Linked Models

You can manually set up a correspondence between phases in the host model and phases in the linked Revit model.

Note: These instructions apply to linked Revit models. They do not apply to linked IFC models.

To map phases in the linked model

  1. In the drawing area of the host model, select the linked Revit model.
  2. Click Modify | RVT Links tabProperties panel (Type Properties).
  3. In the Type Properties dialog, find the Phase Mapping parameter and click Edit.
  4. In the Phases dialog, select the appropriate mapping options for each phase, and click OK.
  5. Click OK to exit the Type Properties dialog.

To apply phase mapping in the host model

  1. Click View tabGraphics panel (Visibility/Graphics).
  2. In the Visibility/Graphics dialog, click the Revit Links tab.
  3. Click the button in the Display Settings column for the linked Revit model.
  4. In the RVT Link Display Settings dialog, on the Basics tab, select By Host View or Custom.

    If you select Custom, for Phase, select By Host View.

  5. Click OK twice to exit the Visibility/Graphics dialog.