When Slopes is selected in the left panel, the right panel displays a table of slope values available in a project.
Slope values can be copied to another project using the Transfer Project Standards feature.
Adding a Slope Value
- Click New Slope.
- In the New Slope dialog, enter a slope value.
If the slope value entered is greater than 45 degrees, a warning displays.
- Click OK.
Deleting a Slope Value
- Select a slope in the Slope Values list.
- Click Delete Slope.
The slope value is removed from the project.
Note: The default 0 (zero) slope value cannot be deleted.
- Click Yes.