A request for quotation (RFQ) is a document sent to a supplier or subcontractor to obtain pricing using data from Cost Management.
There are two ways to generate an RFQ document:
In this article:
The Request for Quotation (RFQ) tab is within the Change Order tab in Cost Management. Tab names can be customized by project administrators within Services.
The item's status automatically updates to Draft after an RFQ is generated from a PCO.
Select the item’s name to open the flyout panel. Editing the RFQ can be done within the flyout panel. In the flyout panel, selectable workflow-based actions will appear to guide you through the change order management process.
For example:
Click the More menu to set the status of the RFQ or delete the item.
Click Export to create an RFQ report.
The Response Due column will be populated when a date is added in the dates section of the flyout panel.
Click the to filter and group the table.
See the available predefined views of the table or save the current view of the table.
Select the icon to edit the position and visibility of columns within the table.
Before you can generate an RFQ document, a project administrator must create the RFQ document template in the Project Admin module. See Create and Manage Document Templates to learn more.
After the RFQ document template is created and a cost item associated to a budget is assigned to a PCO, a project administrator can generate an RFQ. To do so:
Select the Change Order tab.
Select the PCO tab.
Enable the checkbox for a PCO.
Click the More menu and click Cost Change Generate RFQ. Individual RFQs are created for each cost item within the PCO.
Enter necessary values into the Estimated and Proposed columns. You can copy cost item amounts from another column.
Open the newly created RFQ by clicking its name. The details panel opens.
Click Set as Open.
Modify the following fields as required:
In the Documents section, create a document package and add more attachments as required to use for the RFQ.
Choose a supplier name in the Supplier Details section if not selected yet.
Click Request Quotation. The Send Email to Supplier window opens. The supplier contact from PCO flyout is the default recipient. You can change this contact in the:
Fill up all necessary fields, and then click Send.
Modify the fields as required.
Once the RFQ is sent, the next options appear: Set as Proposed, or Rejected, and so on. A supplier will be notified of the quotation request by email when they have a collaborative permission for RFQs. The status is set as Pricing. See the Change Order Statuses article to learn more about the RFQ workflow statuses.
As a supplier:
Once submitted, the system will notify a general contractor by email. They can either accept it or request a revision.
When a revision is required, the process will continue as outlined once it is submitted back to a supplier. If necessary, a formal quotation can be attached by a supplier when responding. Once accepted by a general contractor, the system will notify a supplier by email.
When a change order is in the Proposed, Accepted, and Rejected status, a supplier with collaboration permission can read cost information or download documents in the view-only details panel. Click View Cost Detail in the More menu .
When Accepted, project administrators can request extra revision or generate SCO to finish the change order workflow.
In addition to generating an individual RFQ, you can batch-request quotations from a PCO. A batch-request quotation can be used when a change occurs, and it is unclear who might be affected by this change. To reduce the risk of missing anyone, a batch request to all suppliers can be sent to let them indicate whether affected or not and keep a record of their response.
To create a batch request:
Click the Change Order tab.
Click the PCO tab.
Click the More menu of a PCO and choose Batch Request Quotations.
Add a filter for Contract type.
Select a Supplier.
Enter a Message to be included with the request.
Select a Due date.
If necessary, choose Attachments to include.
Click Send.
Placeholder cost items are generated for each supplier and are shown in parentheses. Suppliers can respond by saying no impact or can propose a quotation.
The placeholder cost items will be converted to regular cost items when a quotation is proposed.
By default, the Response Due date for RFQs is set to seven days after creation. Project administrators can adjust this default setting as follows:
To detach a cost item from an RFQ, expand the row and select the More menu or check the box. The detach button will appear. It will still be part of the PCO.
To delete an RFQ, select the More menu next to the item's name. To delete more than one RFQ, select the box next to the items and click Delete.
You can export a COR, OCO, or SCO report that will contain all details or a minimum number of them. To do so:
Select the Change Order tab.
Switch to the RFQ tab.
Click Export .
Choose one of the following:
Add the Report Title.
Choose the Report Template:
Choose whether you want to include the Cost Item information in the report. By deselecting this option, you can export a report only with the minimum details.
Add an optional message.
Click Run report.
You’ll receive the report by email.
Members with collaborative access are able to export reports from change order tables (PCO/RFQ/COR/OCO/SCO).
For the change order report, the system displays the corresponding cost items along with their amounts. For instance, RFQ reports include proposed amounts. However, the budget code and name are not visible in these reports.