RFI Numbering

When an RFI is sent to the Reviewer, and transitioned to the Open state, administrators and managers have the option to assign a custom number.

BIM 360 supports these capabilities:

Revision RFI Numbers

It is important to use the RFI revision format .1 when creating revision RFIs to ensure proper sorting.

Notice the sort order of the two revisioning methods:

Suggested Numbering

As an RFI is opened, the suggested number is the number of the last RFI created or renamed increased by one. You can override suggested numbers, but are prevented from creating duplicates.

Sort Order

Unnumbered RFIs will sort to the top (Draft and Submitted statuses). You can reverse the sort order using the header columns.

Default RFI Sorting

Assign RFI Numbering

RFI numbers must be added when submitting for review (opening the RFI).

Submitting RFI Custom Numbering

Edit an RFI number to override the assigned number.

Edit RFI Number