A simulation plays your schedule against the model over time. It steps through the schedule using the activity and model object links to show and hide objects as their dates arrive, so the building appears as the Gantt chart progresses.
Use a simulation to:
Watch construction progress visually instead of reading dates in a list
Forma Build prepares the simulation by processing the linked activities and model objects. When it's ready, the model appears below the list and Gantt chart.
Use these controls:
Play: Plays the simulation.
Pause: Pauses the simulation.
Change speed: Select 1X (default speed), 0.5X, or 2X.
Jump to an activity: Select an activity to move the model to its start date. The marker always shows the current date. Playback pauses at that date until you click Play.