Demand Allocation Manager - Allocation Tab

The Demand Allocation Manager is the primary vehicle for allocating demands from a GIS intersection to the desired InfoWater Pro database. Not all of the options shown will be available at any given time. Options will be activated and deactivated depending on the allocation method selected. Inactive options will be grayed out and will not be accessible if no change is required.

Allocation Tab

Apply to Pipes in Domain - If checked, the demand allocation only applies to pipes in the active domain.

Assign Demand to Junctions in Domain - If checked, the demand allocation only applies to junctions in the current domain.

Meter Assign Options - When using the Closest Pipe and the Meter-Pipe allocation methods, you have the ability to determine how meter demands will be divided and applied.

Allocation Scaling Factor - Use this box to normalize demand data. The default value is set to unity (1.0) and may be changed to reflect the actual demand multiplier. It will be necessary to apply scaling factors when water duty factors are expressed in gpm/acre and acreages calculated from a polygon intersection are expressed in sq. ft.  In this instance, use an allocation scaling factor of 1/43560.

Save - Saves and starts the allocation process using the method and options selected.

Options - See Demand Allocation Options.

Close - Close the Demand Allocation Manager.

Allocation Method

Polygon Layer(s)

Meter Configuration

When using consumer/customer meter data to estimate nodal demands, you will need to specify which fields contain the meter record data.

Pipe-Meter Assignment Method