Plan a sprint
Before planning a full sprint, you should plan out the activities expected to be completed in the next sprint. See Plan a sprint activity for more information on how to plan an activity.
To initiate a sprint, two conditions must be met:
- You must have at least one backlog activity selected for the next sprint. The validation script prevents you from proceeding with the project workflow that has no selected activities.
- You must have at least one person entered into the Team field on the project. All activities selected for a sprint are assigned to the team members listed in this field, unless specific assigness are defined on the activities themselves.
Read on to learn how to achieve these requirements.
Add a team
- Navigate to the Innovation Project tab > References section.
- Click Edit.
- Click the Team field and select members to add to the team.
- Click Save.
Add activities to a sprint
- Open the Activity Backlog tab.
- Click Edit.
- In the Next Sprint column, select each activity to add to the next sprint.
- Click Save.