Standard Schedule
Note:
For users with Fusion connected sites, references to the 'Items' workspace should be the 'Components' workspace.
Multiple offset days can be defined in section Package Target Schedule. These offset days will be used upon package creation to calculate the target dates for the given milestones. The dates still can be adjusted per package, which will automatically create the matching milestone entries in the background. This enables tracking of due and delayed activities.
Usage of these offsets and the package target dates is optional.