You can select Precast Concrete Girder or Steel Plate Girder as a bridge type. Changing bridge type causes Bridge Design to recalculate the material quantities needed to build the bridge.
in the
Utility Bar to enter
Edit Mode.
| Bridge Type | Maximum Span |
|---|---|
Precast I Girder Bridge
|
35 meters |
Steel Plate Girder Bridge
|
50 meters (*setting Steel Plate Girder Bridge span greater than 80 meters will create a variable depth girder.) |
Changing the type of an existing bridge (for example, from
Precast I Girder to
Steel Plate Girder) will cause Bridge Design for
InfraWorks 360 to recalculate the material quantities needed. See
To review bridge material quantities for more information.