Machine Utilization
Analyze how each machine is being used within its defined limits.
Previous steps: Improve the Material Flow | Next Steps: Generate a Report
At the end of this exercise, you will have the following information about your drawing:
![](../../../images/tutorial4_mach_use_completed.jpg)
Open the Files and Settings
- Open AutoCAD.
- Navigate to FDU Tutorials > Chapter 2 > Material Flow Analysis_Complete.dwg.
![](../../../images/tutorial4_mfa_complete_dwg.png)
- On the Factory ribbon > Material Flow panel > Transportation option, select the Machine option to activate the Machine Utilization Meters.
![](../../../images/tutorial4_machine_option.png)
- Right click the KWH meter and select Indicators > Utilization Settings from the context menu.
![](../../../images/tutorial4_kwh_settings.png)
Note: The values displayed may differ depending on your selection.
Add a Meter to the Dashboard for Specific Operations
- Hover the cursor above callout 4 (Planing Station) until the meter displays.
- Right click and select Optimization > Add Meter to Dashboard from the context menu.
![](../../../images/tutorial4_add_meter.png)
- Repeat step 2 for callout 2 (Machining Line).
Adjust the Properties of the Planing Station Operation
- In the Material Flow Browser > Routings tab, select Planing Station.
![](../../../images/tutorial4_mat_browse_plan_station_select.png)
- To update the processing time for the Planing Station, go to the Factory Properties > Material Flow Object tab > Properties > section Processing Time and enter 24.
![](../../../images/tutorial4_process_time_set_24.png)
- Review the results of the change. Notice how the percentage of use value decreased and the callout for this operation turned from red to green.
![](../../../images/tutorial4_results_of_change.png)
Adjust the Properties of the Panel Machining Operation
- In the Material Flow Browser > Routings tab, select Operation 3: Panel Machining.
![](../../../images/tutorial4_select_operation_mach_panel.png)
- To update the Processing Time for this machine go to the Factory Properties > Material Flow Object tab > Properties section > Processing Time and enter 25.
![](../../../images/tutorial4_proc_time_25.png)
- Review the results of the change. Notice that the percentage of the use value decreased and the callout fro this operation turned from red to green.
![](../../../images/tutorial4_proc_time_results_mach_line.png)
Repeat the previous steps, adding meters for the remaining operations and adjusting the processing time to acceptable levels.
Note: This image shows an approximation of the final results. Your numeric results may vary.
![](../../../images/tutorial4_mach_use_completed.jpg)
Click the Next steps link below to continue.