Link to External Project Files

One of TimeLiner most powerful features is its integration with project scheduling software. A list of tasks including their start and end dates/times can be imported from a project file directly into TimeLiner.

Note: When opening files in Autodesk Navisworks 2022 that were created in Autodesk Navisworks 2011 or earlier, you may find that the Planned and Actual dates have been swapped. Autodesk Navisworks now uses Planned dates by default instead of Actual dates, as is consistent with most planning applications.

To switch date sets for affected files, edit the data source (see To Edit a Data Source), switch the mapping of the Planned and Actual dates in the Field Selector Dialog Box, then rebuild the task hierarchy (see To Build Tasks from a Data Source).