One of TimeLiner most powerful features is its integration with project scheduling software. A list of tasks including their start and end dates/times can be imported from a project file directly into TimeLiner.
To switch date sets for affected files, edit the data source (see To Edit a Data Source), switch the mapping of the Planned and Actual dates in the Field Selector Dialog Box, then rebuild the task hierarchy (see To Build Tasks from a Data Source).