The Process Linework command processes linework connectivity between points, using a specified linework code set in situations where a linework code set was not previously specified.
You can also reprocesses linework connectivity after you make corrections to the survey point descriptions in the Survey Point Properties Dialog Box.
- Current Figure Prefix Database
-
Specify the figure prefix database.
- Current Linework Code Set
-
Specify the linework code set.
- Process Linework Sequence
-
Specifies the order in which survey point descriptions are processed to determine linework connectivity. Select one of the following:
- By Import Order - processes points in the order in which they are imported. Point names are always processed by import order.
- By Point Number - processes points sequentially by point number (ascending order only).
- Insert Figure Objects
-
Inserts figures in the current drawing.
- Insert Survey Points
-
Inserts survey points in the current drawing.