Explore the Schedule

The Schedule displays the Gantt chart of your scenario. Use the Schedule tab to explore your schedule and set controls on activities.

schedule icon overview.png

1. Activity list and Gantt chart 2. Zoom controls 3. Activity tabs

Display information about an activity

To display basic information about an activity, open the Information tab.

  1. Select an activity.
  2. Click to open the Information tab.

Display the constraints on an activity

To show, add, and remove constraints from an activity, open the Controls tab.

  1. Select an activity.
  2. Click to open the Controls tab.
Tip:

If you specify a date to an activity that is outside the current date range of the Gantt chart, you will lose sight of the activity. Click Reset to zoom out and frame the Gantt chart so that it displays your whole schedule once more.

Display the dependencies of an activity

To show all the dependencies of an activity, open the Dependencies tab.

  1. Select an activity.
  2. Click to open the Dependencies tab.

Display the calendars for an activity

To show the standard work week, and the calendar for the tasks of an activity, open the Calendars tab.

  1. Select an activity.
  2. Click to open the Dependencies tab.

Zoom in and out

Easily zoom in and out of the Gantt chart with the zoom tools:

  • Zoom in and out of the chart with zoom in out. You can also use Ctrl+Scroll wheel while hovering over the chart to zoom.

  • Zoom to a specific date range by entering dates in zoom calendars.

  • Quickly zoom in a range with draw zoom.

    draw zoom animation

Reading the Gantt chart

The Gantt chart illustrates your schedule as a series of bars in a calendar grid. The Gantt chart used in Flow Generative Scheduling uses the following symbols.

Use the Customize menu to choose what to display in the Gantt chart.

Activity types

Image of summary Summary
Image of milestone (start) Milestone (start)
Image of milestone (end) Milestone (end)
Image of task Task
Image of task This activity has no issue
Image of red activity This activity has an infeasible constraint
Image of hatched activity (grey) This activity is locked
Image of hatched activity (blue) This summary is partially locked
Image of hatched activity (red) This activity is partially locked with infeasible constraints

Locked activities happen when the schedule is imported with activities that start in the past.

Activity names and dependency indicators

Hide or show the activity labels with the option Customize > Show labels.

Image of activity label Summary with its label name

Hide or show the activity dependencies with the option Customize > Show dependencies. If the predecessors or successors of an activity are hidden from view, then the activity has dependency indicators next to it.

Image of dependency indicator 1 (incoming) Indicates the activity has one hidden predecessor
Image of dependency indicator 6 (outgoing) Indicates the activity has six hidden successors

Finding activities

The Filter menu offers various filters that allow you to quickly navigate your schedule.

animation filter gantt chart

Find all the tasks that use a specific resource class

  1. In the Schedule tab, open the Filter menu.

  2. From the Resources section, select the resources.

    The Gantt chart updates as you select resources, and displays only the tasks that use the selected resource classes.

Find all activities with infeasible constraints

As you add more constraints to a schedule, some can become infeasible to enforce. The Filter menu makes it easy to locate activities with this type of constraints.

  1. In the Schedule tab, open the Filter menu.

  2. From the Constraints section, select Has infeasible constraints.

    The Gantt chart updates to display only the activities with infeasible constraints.