About Applying Rules to Pipe Network Parts
You can apply rules to pipe network parts to ensure that certain conditions are flagged, and to ensure that parts are placed in correct locations.
About the Cover And Gradient Pipe Rule
This rule ensures that a pipe slopes appropriately and warns when a pipe is placed too close to a ground surface.
About the Cover Only Pipe Rule
This rule is intended for laying out pipes in a pressure-based pipe network where pipe levels are determined according to a specified depth below a terrain.
About the Length Check Pipe Rule
This rule governs the behaviour that produces a warning condition on a pipe if the pipe length exceeds the value specified for the maximum pipe length, or is less than the value specified for the minimum pipe length.
About the Pipe To Pipe Match Rule
This rule governs how a pipe level is determined in a pipe network that contains only pipes (no structures), and or when a pipe is inserted onto an existing pipe to break the pipe.
About the Set Pipe End Location Rule
This rule allows you to set the start and end locations of the pipes to be at the structure centre or at an offset relative to the structure's inner or outer wall. It also includes an option to specify whether to hold the pipe slope or pipe invert when moving the pipe end location with this rule.
About the Pipe Drop Across Structure Rule
This rule compares all pipes connected to a single structure and ensures that pipes enter and exit the structure according to the specified drop value.
About the Set Sump Depth Structure Rule
This rule sets the sump level of junction structures based on the user-specified parameters and the invert levels of pipes attached to the structure.