BIM 360 Plan has five activity types that you can track in your projects.
The activity name is a required field. The assigned company and person, as well as the duration, finish date, and crew size are filled in for you.
- Click + Activity > New Activity.
- Select an activity type. The default is Task.
- Specify the status. The default is Open.
- Specify the name.
- The associated company is pre-populated based on your sign in. You can select a company to associate with the task. Type the company name to narrow the list.
- You can select another person to assign the task to. Type a name to narrow the list.
- Select the location. Locations are defined as part of project administration.
- For Schedule, the duration, finish date, and Crew Size are automatically generated. Adjust as needed.
Click Extended Workdays to add weekend days or holidays to the schedule.
- For Details, select a work breakdown structure (WBS), and optionally enter a description.
- Click Save.