Change Administrator and Responsible Engineer Tasks
Change Administrators and Responsible Engineers have the greatest range of permissions and control over the change order process.
When you create a change order, you select a routing definition requiring one or more participants to approve the change order.
Before you create a change order: Make sure that a routing has been created by the administrator. The routing should contain everyone that needs to review, be responsible for, and approve the change order.
Permission Requirements
You must have one of the following permissions to be a Change Administrator:
- Administrator
- Change Order Editor
The data associated with an open change order can be modified by the Change Administrator.
In the Open and Review State
Change the state of the item. Changing the state to Work In Progress allows the item to be edited. Changing it to In Review locks the item, preventing the item from being edited.
Note: When you change the state of a released item to Work In Progress, a new revision is created. If the Bump revision action is set to None in the Lifecylce Rules dialog box a new revision is not created.When Change State is disabled, the lifecycle state of the item changes to In Review.
Attach or remove files.
Create a markup from an attached .dwf file and add a comment to the markup.
Customize the email notification
Add or remove items.
Add, remove, or edit user-defined properties
Open State
The Change Administrator can edit the title, edit the value of a user-defined property, and change the attachment of an open change order.
The Change Administrator can perform the same editing tasks in the open state as in the state when the change order is first being created with one exception: The specified numbering scheme cannot be changed.
Change the lifecycle state of the item by using the change state command in the context menu of a selected item.
Work State
When a change order enters the Work state, the Responsible Engineer is notified that there is a change order requiring attention:
- The change order number is added to the work list of each participant.
- An e-mail message is sent to each person on the routing list if they have subscribed to e-mail notification for change order events.
Anyone can view the status.
A reviewer can view, add, and reply to change order comments.
The Responsible Engineer can edit the change order, as well as make the necessary revisions and then submit the change order for review.
Review State
When a change order enters the Review state, routing participants are notified that there is a change order requiring attention:
The change order number is added to each participant's work list.
An e-mail message is sent to each person on the routing list if they have subscribed to e-mail notification for change order events.
A reviewer can view, add, and reply to change order comments.
Anyone can view the status.
Approved State
A participant with approver status can approve a change order.
The Change Administrator can change the life cycle state of the item by selecting an item and selecting Change State from the context menu. Only the allowable state changes are displayed.
Items are effective immediately when released.
Rejected State
A participant with Approver status can reject a change order.
As a Change Administrator, you can do the following to a rejected change order:
- Cancel the Change Order
- Reopen the change order