Synchronize Tasks with Project Changes
Any changes to tasks and task data in the external data source can be easily updated in TimeLiner.
Refresh Tasks to Reflect Project Changes
- Make changes to the project in the scheduling software, and save it.
- Load your model into Navisworks (see Open Files if you need help).
- Click Home tab > Tools panel > TimeLiner
, and click the Data Sources tab in the TimeLiner window.
- Click the Refresh button and select Selected Data Sources or All Data Sources.
- In the Refresh from Data Source Dialog Box select one of the following options and click OK.
- Rebuild Task Hierarchy. Choose this to re-import all tasks and associated data from the selected project file(s), and rebuild the task hierarchy on the Tasks tab.
- Synchronize. Choose this to update all existing tasks in the Tasks tab, with the latest associated data from the selected project file(s) (for example, Start and End dates).
Tip: You can also right-click data source in the Data Sources tab and select the Synchronize or Rebuild Task Hierarchy option.