Indicates whether there are any background calculations in progress for this document.
Namespace: Autodesk.Revit.DB
Assembly: RevitAPI (in RevitAPI.dll) Version: 26.1.0.0 (26.1.0.34)
Syntax
C#
public bool IsBackgroundCalculationInProgress()
Return Value
BooleanReturns true if the document has any data calculation in progress and false otherwise.
Remarks
When a document has background export in progress, users cannot perform document close. For any other background calculation in progress, users cannot perform the following operations:- Save/Close the document.
- Export/Print the document.
- Synchronize to central, in worksharing environment.
- Create a steel element.
- Copy/Mirror/Rotate a steel element.
- Edit the sketch of plate element.
- Edit a custom connection.