To Synchronize Individual Display Settings With AEC Standards

Use this procedure to synchronize display settings in a project drawing with the project standards.

Note: Display settings should always be synchronized with the latest standard settings. Out-of-synch display settings in a project can cause objects to be displayed inconsistently.
  1. Open a project drawing.
  2. Click Manage tabStyle & Display panelDisplay Manager.
  3. In the Display Manager tree, navigate to the display setting you want to synchronize.

    You can synchronize the following items:

    • display configurations
    • display sets
    • display representations
  4. Select the item in the tree, right-click, and select Synchronize with Project Standards.
  5. In the Synchronize Drawing with Project Standards dialog box, select the items to synchronize.
  6. Click OK to start the synchronization process.