To Create a Drawing List Report

Extracts the settings of each drawing in the project and displays in a report.

  1. Click Project tabProject Tools panelManager. Find
  2. (Optional) Select folders in Project Manager.
  3. Right-click the project or folder name, and select Drawing List Report.
  4. (Optional) In the Drawing List Report dialog box, click Format and browse to a report format file.
  5. Click New Report.
  6. Select the drawings to process.
    Note: Folders selected in Project Manager are preselected in the Select Drawings to Process dialog box.
  7. Click OK.
  8. Do any of the following:
    • Change the report format
    • Save to a file
    • Place the report as a table
    • Print