Add and manage QA process relationships

The Relationships (relationships) tab is where you link a quality assurance (QA) process to another QA process or another requirement. You may specify how the QA processes/requirements depend on each other. This enables you to follow up on other QA processes/requirements that depend on one you've just completed.

Note: You cannot create relationships to requirement tasks or QA tasks.

To add a relationship:

  1. From the list of QA processes, select the QA process to which you want to create a relationship.

  2. Open the Relationships (relationships) tab.

  3. Click Add.

  4. From the first drop-down list, select the option that specifies how the QA processes is linked to the other QA process/requirement.

  5. In the box beside the drop-down list, begin typing the name of the QA process or requirement you want to link this QA process to.

    A list of matching QA processes/requirements is shown.

  6. Click the QA process/requirement you want to link to.

  7. Click Add.

The relationship is added and shows the status of the linked QA process/requirement.

Repeat the above steps to add more than one relationship to a QA process.

Note:
  • The relationship you added here is unidirectional, meaning the same relationship does not appear on the QA process/requirement you linked here. You would need to manually add the relationship going the other way.
  • Upchain does not enforce these dependencies. It is up to you to specify the relationships and then follow through with them as you work through the QA process list.

Remove a relationship

  1. From the list of QA processes, select the QA process from which you want to remove a relationship.
  2. Open the Relationships (relationships) tab.
  3. Beside the relationship you want to remove, click Delete (Document_Delete_icon).

The relationship is removed.

Was this information helpful?