Show the task assignee in the Gantt chart
Note:
For users with Fusion connected sites, references to the 'Items' workspace should be the 'Components' workspace.
To be able to show the task assignee in the Current Sprint Activities Gantt chart tab for innovation projects, you must enable this option in the Administration settings.
Open Administration > System Configuration > General Settings.
In the Project Management section next to Display Assignee, select Yes.

Click Save.
See Configure General Settings for more information.
