Share

Show the task assignee in the Gantt chart

Note:

This template is not currently available for Fusion Manage Extension sites.

To be able to show the task assignee in the engineering project Gantt chart tab, you must enable this option in the Administration settings.

  1. Open Administration > System Configuration > General Settings.

  2. In the Project Management section next to Display Assignee, select Yes.

    display assignee

  3. Click Save.

See Configure General Settings for more information.

Was this information helpful?