Share

Task Status Update

Performing a task may take some time and project managers may request frequent updates about the task status. This can be accomplished very easily by the Assignee while the task is in status In Work thanks to the list of defined progress levels shown as workflow actions:

alt text

Once the user selects the right level, he can also provide comments to share feedback with the team:

alt text

Such status updates are shown in the Status section of the task details page, including a graphic progress bar, the date of the last update and the given workflow comments that were provided. In addition, the Comments Log in section Workflow Comments History provides full traceability of all changes to the task status and given comments.

alt text

This status updates information is also used to update the project’s Gantt to enable real time progress tracking by the project manager:

alt text

Was this information helpful?