Project Attributes
The details page of Projects is divided into the following sections:
Basic | Holds all the required inputs like Title, Start Date and Template. The number on top is generated automatically. The Priority indicator is based on inputs in section 'Priority Assessment':![]() |
Details | Optional data can be managed in here for filtering and reporting purposes:
|
KPIs | Automatic indicators are listed in here. They are useful to enrich your Projects workspaces views.![]() The first column, Progress, is based on the state of each Phase. The squares follow a specific color coding:
The Status column is based on the values entered in the section 'Status Report' The 'Current Phase' field reflects the current status of the project. The 'Phase Progress' field shows a progress bar to indicate the percentage of completed tasks within the current phase. |
Project Phases | The schedule of the projects’ phases can be reviewed in here:
|
Next Gate Review | This section is used to control the next gate review & approval. As the project enters a new phase, the list of 'Required Approvers' will be set to match the Project Template’s list of approvers for this phase’s gate review. Additional Approvers can be added in the given field. As the given gate review status is reached, the required and additional approvers will be requested to approve the project and will therefore be copied to the list of 'Remaining Approvers'. If neither required nor additional approvers are defined, the project owner will be set as the only remaining approver. |
Gate Reviews | If project buffers are used for the transition process from one phase to another, the phase completion dates will be different than the ones of the related gate reviews. This is reflected in this given section which works in a similar manner as the date fields in section 'Project Phases'. The project scheduling will take into account the gate review durations / buffers defined in the selected 'Project Template' and shown in here: If these buffers are not set to 0, the gantt will also block a given timeframe for these reviews based on the duration defined. These buffers become important when the schedule gets changed later on: If a gate review has a buffer of 5 days defined and the preceding phase finishes late by 2 days, the gate review’s duration will be reduced to 3 and thus not impact the schedule of succeeding phases. However, if the given phase finishes late by 7 days, the gate review will be reduced to 1 day and as the buffer cannot compensate the delay, the succeeding phases’ dates will be postponed. The remaining delay of 3 days (7 days delay - 5 days buffer + 1 day for the gate review) may be compensated by the next phase’s buffer (if defined). Often times, gate reviews fail and require rework. This is indicated by the Review Counters which get increased every time a given gate review status is reached. |
Priority Assessment | To define the priority of a project compared to others, certain criteria can be assessed. The priorities listed in here drive the overall Priority of the project shown in the Basic section. |
Project Members | This section can be used to automate the task assignment process. If tasks are assigned to teams within the Project Template or the Task Planning tabs of Project Phases, but not to assignees yet - and if there is a project member defined for this team in this given section, then the task will be assigned to this member automatically. It is recommended to only have one person per team defined as this given user will become the assignee of all tasks for this team. Further users of the same team are not taken into account. |
Efforts Tracking | This section is fully automated and can be used to track the total effort of a project, but also to compare the planned vs. actual efforts. While the project is in Planning status, the 'Planned Efforts' will be calculated automatically based on the Planned Efforts of tasks listed in the Task Planning of related Project Phases. Once the project leaves the Planning status, all changes to the Task Planning will result in updated total efforts in the Expected Efforts row. As Project Tasks are set complete, the efforts that have been entered for the task will be added to the Actual Efforts of the related phase on project level. The Deviation row automatically compares the Planned Effort against Actual Efforts (once available) or the Expected Efforts. |
Budget | Budget information can be provided in this section to determine the total planned and actual cost of a project. Deviations from plan will be calculated and highlighted in the KPIs section. |
Status Report | This section can be used to frequently report on the status of the project in regard to Schedule, Resources, Budget and Risks. The current status will be highlighted in the KPIs section. |
Deliverables | Key deliverables of the NPI project can be referenced in this section, including the Specification document, Bill of Materials, Design Reviews and others. If you downloaded this template from the Template Library, these fields will have to be set as linking picklist fields first by the tenant administrator |